And Wisconsin is next.
The proposed 345-kilovolt lines, on towers as high as 150 feet placed every 1,000 feet, would run from the Twin Cities to Rochester, Minn., and then to substations in La Crosse or Holmen, Wis.
The CapX2020 project, estimated to cost $1.7 billion in 2007, is comprised of four power lines, including one that would cross the Mississippi River at one of three cities: Alma, Wis.; Winona; or La Crescent, Minn.
Two additional 345-kilovolt lines — one from Fargo, N.D., to the Twin Cities and one from Brookings, S.D., to Monticello, Minn., as well as a 230-kilovolt line from Bemidji, Minn., to Grand Rapids, Minn. — are included in the project, proposed by 11 utilities. Xcel Energy and Great River Energy are applying for approval to regulatory agencies on behalf of the 11.
But critics question the need for the massive lines and say the public hasn’t been properly informed about the proposal.
Growing demand
Tim Carlsgaard, who works for the 11 utilities as communications and public affairs manager for CapX2020, said energy use across the region continues to grow, prompting the push to deliver reliable, affordable energy. In Minnesota alone, he said, energy use has doubled since 1980.
The upgraded lines would meet future needs, he said, and revamp a transmission system that hasn’t had a major overhaul since the 1970s.
Carlsgaard said the utilities aren’t going to build more lines than necessary.
“I think we have a very strong case,” Carlsgaard said.
On the other side
Paula Maccabee, a St. Paul attorney representing the Citizen’s Energy Task Force in the Public Utilities Commission hearings in Minnesota, said the utilities have overstated the demand for the line going to La Crosse.
“The utilities have been stacking the deck to make it look like this project is needed,” Maccabee said, “but once you get behind the data, you see how it’s not true.”
If the Twin Cities-Rochester-La Crosse line were not built, she said, power company officials have testified that enhancements to the current transmission lines would not be needed until 2026 or 2028 in Rochester.
“And that’s without studying the conservation aspects,” Maccabee said. “The benefits are not clear and certainly have been exaggerated, and the harms are unavoidable.”
Not so, said Carlsgaard. “We’re not going to scare people and say, ‘(Do this) by 2010 or 2015 or your lights are going to go off,’” he said. “That’s irresponsible. We’ve proven in everything we’ve put forward there’s a need for these lines.”
Another solution?
“If we go to more renewables, we don’t need this expensive high-voltage system,” Minnesota state Rep. Ken Tschumper, DFL-La Crescent, said during a forum he organized July 31 at La Crescent’s American Legion for those concerned with CapX2020.
“Renewable systems can feed into the grid as well,” he said.
It’s also the law, Tschumper said, as Minnesota passed a renewable energy standard in 2007 mandating 25 percent of all electricity used in the state be generated from renewable energy sources by 2025.
Renewables are a very important part of meeting future resource needs, Xcel spokesman Brian Elwood said, but the company still needs sufficient transmission lines in order to get the resources to the customers.
Eleven percent of Xcel’s electricity now is generated from renewable sources, Elwood said, and by 2025, Xcel expects 25 percent to 30 percent of its electricity will come from wind energy, along with other renewable resources such as biomass, hydropower, and burning garbage and wastewood.
The risks
Patrick Caffrey, president of Friends of Trempealeau Refuge, said he’s not debating the need for the project, just the location.
“We’re encouraging the utilities to choose routes that minimize the length of lines in the river valley,” Caffrey said.
The Mississippi River is a major flyway for migrating birds and bats, he said, and he’s concerned how wildlife will be affected by the lines spanning the waterway.
The proposed crossing also could jeopardize the area’s scenic corridor and harm tourism, he said.
“If they cross at Alma and follow it along the river valley to La Crosse or Holmen, that would be the worst option,” he said.
Public health
“It’s clear that a power line causes harm,” Maccabee said. “What the World Health Organization says is they’re considering electromagnetic fields as a possible carcinogen. There’s a consistent association with EMFs and childhood leukemia.”
There isn’t enough laboratory evidence to classify EMFs as a definite carcinogen, she said, but research such as the BioInitiative Report shows reason for concern.
“There is substantial evidence, and at the very least it should cause people to be cautious,” she said.
But Carlsgaard counters that the lines will be far enough removed from the public. Towers 150 feet high carrying 345-kilovolt lines are built with a 150-foot right of way, Carlsgaard said.
By law, they must use an existing crossing, and CapX2020 aims to keep them away from residential areas, he said.
“We have people working on health issues, following the debates and looking at the studies,” Carlsgaard said. “We’re very involved.”
Added Chuck Thompson, manager of siting and regulatory affairs at Dairyland Power Cooperative: “There has been a significant amount of research done over the last 25 years, and today there hasn’t been a correlation between electromagnetic fields and cancer.”
Skeptical of the skeptics
“If we’re going to meet the Wisconsin target of renewables, we’re going to need this line,” said Wisconsin Assembly Speaker Mike Huebsch, R-West Salem. “We need the wind power that Minnesota has to offer.”
The Wisconsin target is 25 percent renewable energy by 2015, Huebsch said. That makes transmission lines — such as the one proposed for the La Crosse area — necessary, he said.
Pat Morrison, who moved to La Crescent in 2005 after living outside Sacramento, Calif., for more than 20 years, said she’s lived through “phenomenal” expansion on the coast.
“With that growth, they needed more water, they needed more electricity — all of that,” Morrison said.
She doesn’t oppose the project at all, she said, and doesn’t see the reason for all the uproar.
“I think it will be done very carefully. They have to in this day and age,” she said.
Approval process in Minnesota
Establishing such large transmissions lines in Minnesota is a two-step process, Thompson said.
“One is to go through a hearing process on the need,” he said. “The second, if they approve the project, then we come back and we’re talking just about routes.”
Notices went out in July 2007 to 72,000 Minnesota landowners and local officials, said Carlsgaard. In August 2007, 2,050 Wisconsin landowners were notified about the proposal.
The Minnesota Department of Commerce then held 10 public meetings in December 2007, he said.
The Minnesota Public Utilities Commission convened an evidentiary hearing in July that will conclude this month.
In addition, more than 100 informational meetings were conducted in 2006 and 2007 for the media and public officials in South Dakota, North Dakota, Minnesota and Wisconsin.
By May 2008, 60 open houses and 36 routing work group meetings had been open to the public to attend, at Minnesota sites such as Winona, Wabasha, Alexandria, Marshall, Lakeville, Fergus Falls, Red Wing, Rochester and Cannon Falls, as well as La Crosse and Centerville in Wisconsin, Carlsgaard said.
“None of this is required by the Minnesota regulatory process,” Carlsgaard said. “And, we still have to go through the whole Wisconsin regulatory process.”
But opponents of the project still argue that not all the residents in areas along the corridor were properly informed.
Once the evidentiary hearing is through and public comments no longer are accepted, further meetings in Minnesota will focus on determining the route rather than determining need, opponents say.
Both sides of the debate strongly encourage Minnesota residents to submit written comments to Minnesota Administrative Law Judge Beverly Heydinger.
Public comments in Minnesota will be accepted until Sept. 26.
Wisconsin timeline
“The need and the routing are addressed in one process in Wisconsin,” said Xcel Energy project leader Tom Hillstrom, “and that’s called the certificate of public convenience and necessity.”
Hillstrom said CapX2020 likely will file an application for the certificate in early 2009. He expects the Wisconsin regulatory process of public meetings and hearings on the state certificate to take one to two years before the Public Service Commission rules on the application.
The Minnesota portion of the project would end either in the Winona or La Crescent areas. Crossing the Mississippi at Alma or Winona would mean continuing the lines to an expanded substation in Holmen or a new substation north of Holmen, Hillstrom said. A La Crescent crossing would lead to a substation in La Crosse.
“The earliest that a route could be approved by the two states is 2010,” Carlsgaard said.
What next?
Discussions already are under way between Xcel and American Transmission Co. for a 345-kilovolt line to run east to southeast out of La Crosse, Carlsgaard said.
That line would address energy needs in the 2023 to 2025 time frame, he said.
“There’s going to be more transmission lines. We’ve said that before,” Carlsgaard said. “These are not going to be the last of what we’re going to have to propose.”
La Crescent, Minn., resident Jeremy Chipps, a Citizen’s Energy Task Force member who has vocally questioned the need for new high-voltage lines, successfully brought about a resolution from the La Crescent City Council opposing the lines coming through the city.
“My initial thought when I first came upon this was, ‘Where would the line be going after it comes to La Crosse?’ ” Chipps asked.
Ryan Stotts is a reporter for the La Crosse Tribune.
CapX2020 to affect Xcel customers’ rates
Xcel concedes that with a $1.7 billion price tag for all four lines, the CapX2020 project will affect Xcel customers’ rates.
Just what those rates will be has not been made clear, said Paula Maccabee, attorney for the Citizens’ Energy Task Force.
“People have a right to have at least a ballpark estimate on how much this is going to cost,” Maccabee said.
Once the certificate of need has been approved, Xcel can start charging customers, said Tim Carlsgaard, communications and public affairs manager for CapX2020. The costs escalate as the project reaches what he called “the height of construction,” he said, “when we’re spending the most money.”
By 2013 to 2015, Customers likely will pay an additional $2.25 per bill for the project, he said.